Leeds City Rail Station

Milestones

  • Public consultation on proposals

    January 2020

     

    -

     

    March 2020

    Activities included an online survey, face-to-face consultation opportunities in Leeds City Station, and engagement with businesses and affected stakeholders.
  • Funding secured subject to business case approvals

    Spring 2021

     

    -

     

    Complete

    Funding secured through the Leeds City Region Transforming Cities Fund programme
  • Preliminary work begins on site

    23 May 2022

     

    -

     

    April 2023

    Preliminary work begins on-site, including drainage and kerb re-alignment
  • Main construction work begins

    March 2023

     

    -

     

    September 2025

    Main construction work begins on site.
  • New Station Street partial closure

    19 May 2023

     

    -

     

    October 2024

    New Station St will be closed to through vehicles and pedestrians turning left from the station's main entrance towards City Square. Boar Lane can be accessed by turning right out of the station's main entrance.
  • Scheme due for completion

    September 2025

     

    -

     

    Upcoming